CONSTRUCTION OF MOTORWAY BLACE

Name of Contract Employer’s Contract Value of Work Estimated Completion Date
Construction of Motorway Blace Public Enterprise for State Roads of Republic of Macedonia 14.294.329 Euro August 2023

CONSTRUCTION OF MOTORWAY BLACE

On 17.02.2020 GD Granit AD signed an agreement with the Public Enterprise for State Roads for Construction of the Motorway A4, section BCP “Blace” – Skopje (Interchange”Stenkovec”), Subsection 1- expansion of the existing road A4 from BCP “Blace” to the village Blace to level of motorway and construction of part of motorway with Interchange for connection with local road with the village of Blace.

CONTRACT ID

Contract name:
Construction of Motorway Blace

Brief Description of the Works performed:
Road construction works

Name of Employer:
Public Enterprise for State Roads of Republic of Macedonia

Gallery

GRANIT PRODUCTION

Our strategy is to be economically independent and self-sufficient for most of its basic resources. Therefore securing resources such as rock, concrete and asphalt is of outmost importance.

  • 9
    CONCRETE PLANTS
  • 7
    ASPHALT PLANTS
  • 7
    STONE QUARRIES
  • 11
    PRODUCTION FACILITIES